E Jetty is now fully completed with water and 240v power to all berths.
H jetty has also been fitted with water and 240v power, but we are still constructing the mooring fingers for the last 16 berths. These final 8 fingers should be done by the end of the week or early next week.
Invoices and contracts for all E, F G & H jetty berths are on their way to all customers who have booked, start date being 1st November 2007 if the vessel is not present in the marina yet.
There are a few minor finishing touches to be done to the access ramp as we await the steel footplate from the galvanising contractor and mooring post fenders (recycled tyres) should also be added by the end of the week. PL.